Works on the Vaprio d’Adda - Bellinzago L. cycle path in progress
Work continues on the cycle path that will connect Vaprio d’Adda to the shopping center in Bellinzago L., forming a radial route that will connect the future Line 3 with Line 4 of the Biciplan of the Metropolitan City of Milan.
In fact, the segment in Vaprio d’Adda has been completed in recent days, and by September the cycle path will reach Pozzo d'Adda.
At the same time, work is also underway in Bellinzago L., from the roundabout towards Vaprio, where curbs have been laid and the path is ready for paving.
The Metropolitan City technicians have inspected the work carried out, and the company has regularly laid 300m of draining concrete. In the coming days, the planned work will continue.
The work will be completed by next spring. Additionally, the connection to the M2 in Gessate, which is currently difficult to reach safely, is under study.